Our datacenter hardware move is complete. Demolition has begun in our old computer room. 8TB of data travelled over the network to a Sun Microsystems NAS device in our new facility prior to hardware migration. Systems making the transition travelled by truck. Legacy systems were decommissioned in place. Services are returning as systems are re-racked and configured for new network segments.

CR150-vacant-thumb.png

More to follow.